June 20, 2013

A Case of the Vapors – Does New Jersey’s Newest Vapor Intrusion Technical Guidance Foreshadow a Return to the “Old Days” of Environmental Regulation in New Jersey?

Posted on June 20, 2013 by Kenneth Mack

Enacted in May 2009, New Jersey’s “Site Remediation Reform Act”, N.J.S.A. 58:10C-1, et seq. (“SRRA” or “Act”) was heralded by the State’s Department of Environmental Protection (“NJDEP”) as a “new world order” for the State’s site remediation regulation.  Four years later, its imposition remains a “work in progress”.

Belatedly following Massachusetts’ lead, the Act largely privatized site remediation by placing most decisions, including the ultimate provision of final remediation approval, in the hands of state-licensed professionals, called “Licensed Site Remediation Professionals” (“LSRPs”).  It replaced NJDEP’s former “command and control” approval process, which tended toward extreme micro-management of each case.  Instead, LSRPs are supposed to use their professional judgment in effecting remediation.

Interestingly, much of the impetus for the SRRA came chiefly from the Government, compelled by its enormous backlog of unresolved cases: it was not unusual for remedial reports to languish on NJDEP desks, awaiting action, for years.  Moreover, NJDEP had little or no knowledge of many sites on its “known contaminated site list” which numbered anywhere from 10,000 to 15,000 (the fact that that number was unclear was itself troublesome).  Indeed, one of the precipitating causes of the Act was a vapor intrusion case in which it was belatedly discovered, in 2006, that a child day care center had been built, and was operating, on a site which formerly housed a thermometer factory.  This site should have been (but was not) cleaned up under the State’s ISRA law when the factory closed in 1994.  The site had been classified as one of “low” concern, so it was not inspected by NJDEP until twelve years after such closure.  The discovery of these circumstances caused public consternation, followed by litigation and, ultimately, legislation.  

Although the environmental consultant community enthusiastically welcomed the new law (almost immediately dubbed the “environmental consultant right to work act”), individual LSRPs continue to have difficulty weaning themselves away from the “security blanket” of prior department approval of their actions.  These fears are understandably heightened by the statutorily enjoined random audit of at least ten percent of LSRPs annually by the LSRP Licensing Board and the Department’s separate ability to audit final remediation approvals, (called “Response Action Outcomes”, or “RAOs”), for up to three years after issuance.  

Partly in response to the LSRPs’ expressed need for some certainty, NJDEP has been steadily adding to the scope and detail of various technical guidance documents, the most recent one of which is its “Vapor Intrusion Technical Guidance (Version 3.1)” issued in March of this year. At 184 pages, with appendices, this guidance (“VI Guidance”) is nearly twice as long as the next-largest NJDEP “guidance document” and far longer than similar VI guidance issued by authorities in neighboring states.  Indeed, its length is nearly that of OSWER’s External “Review Draft” “Final Guidance for Assessing and Mitigating the Vapor Intrusion Pathway from Subsurface Sources to Indoor Air”, whose issuance it preceded by about a month.  Predictably,  the two documents do not exactly mesh seamlessly.  

The prescriptive nature of the VI Guidance is equal to its heft and seemingly contrary to the Act’s proclaimed conferring of discretionary judgment upon LSRPs.  More troublesome is the fact that the various detailed dictates to LSRPs in the VI Guidance have been translated into a welter of forms that must be filed by the LSRP at various points in the VI remedial process.  These new forms –which are apt to change with some frequency – are all “machine readable” and, in light of the draw-down of experienced NJDEP personnel caused by government cutbacks and natural attrition, are increasingly reviewed by machines, rather than experienced personnel, at least in the first instance.  This seems likely to produce an exaltation of form over substance that does little to foster actual remediation.  Moreover, departures from the VI Guidance must be supported by the LSRP’s explanation of rationale under a pre-SRRA regulation entitled “Variance from Technical Requirements”.  Few such “variances” were ever permitted under this regulation in the past.  The fact that such “departures” may be substantively reviewed by NJDEP only after the final RAO is issued and, if denied, would result in the RAO’s invalidation, creates an added “chilling effect” on an LSRP’s consideration of any such deviation, however warranted.  And, while NJDEP personnel continue to be available to LSRPs for consultation and advice, it is unclear what effect, if any, reliance on such advice would have in any subsequent audit of an RAO.  

It may be that the VI Guidance is sui generis and that its overly doctrinaire approach will not be followed by NJDEP in other areas of remediation.  If not, the “new world order” of the SRRA may morph into something that looks very much like NJDEP’s  “ancien regime”.  Or maybe I just have a case of the vapors.

Tags: vapor intrusionNJDEPguidanceregulationNew JerseyLicensed Site Remediation ProfessionalLSRPSite Remediation Reform Act

Air | Hazardous Materials | Regulation | State

Permalink | Comments (0)